Smart Systems
Client Smart Systems
Location Yatton, North Somerset
Construction Value £5 800 000
Project 15 000 sq ft Factory Production Line Extension
Design of the mechanical and electrical systems to support a new production and warehouse facility including:
Enabling works to the existing HV mains and medium pressure gas supply
- installation of wind Turbines
- installation of new paint plants
- installation of new ventilation systems
- modifications to compressed air systems
- modification to industrial water and demi water serving a new vertical paint plant
- general lighting, power and fire alarm systems
- new process cooling water systems to support the installation of a new aluminium press
- evaporative cooling systems to the existing production warehouse
- M&E services to new office accommodation
- fire hydrant mains and hose reels
Preparation of a sustainability and energy report for planning purposes as well as general advice on renewable energy solutions
- daylight dimming installed to reduce energy consumption from artificial lighting
- two 500kW wind turbines installed at the Smart Systems site
- 650kWp of roof mounted Photovoltaics installed
- energy efficient gas fired boilers installed to serve staff areas